| Restrictions | OK |
|---|---|
| Jurisdiction | Employment Relations Authority - Wellington |
| Reference No | WA 4A/06 |
| Determination date | 29 March 2006 |
| Member | G J Wood |
| Representation | G Ogilvie ; R Foitzik |
| Location | Wellington |
| Parties | About Demolition and Contracting (2003) Ltd v Greening |
| Summary | COSTS - Unsuccessful personal grievance by RG (respondent/applicant) and unsuccessful breach of contract claim by ADCL (applicant/respondent) - 1 day investigation meeting - ADCL sought contribution towards total costs of $5,805 - RG alleged costs should lie where they fall - Key focus of investigation was personal grievance and additional work required of ADCL in order to strengthen evidence which demonstrated RG's explanations were inadequate and misleading - Only a few minutes spent on ADCL's damages claim - Significant contribution to ADCL's costs appropriate which had to be offset by ADCL's failure to pay RG all money owed upon dismissal and fact of ADCL's unsuccessful claim |
| Result | Costs in favour of applicant/respondent ($2,500) |
| Number of Pages | 3 |
| PDF File Link: | wa 4a_06.pdf [pdf 11 KB] |