Restrictions OK
Jurisdiction Employment Relations Authority - Auckland
Reference No AA 128A/10
Determination date 26 July 2010
Member R Arthur
Representation F Chen (in person) ; J Douglas
Location Auckland
Parties Chen v Banclogix Ltd
Summary COSTS – Unsuccessful application to raise grievance out of time – Applicant exercised right to challenge previous determination out of time – Authority found usual process to determine costs on own investigation – Respondent sought $5000 as reasonable contribution to $7266 actual costs – Applicant alleged witness statements and documents not verified in Authority investigation – Applicant sought costs to lie where the fall – Authority found appropriate to follow notional daily rate – Found usual daily rate to apply – Found while some merit in respondent’s arguments that applicant unnecessarily increased costs, no upward adjustment of daily rate appropriate given evidence – Authority ordered applicant to pay respondent $3,000 contribution to costs – Authority noted arrangement may be required for applicant to pay costs in instalments over extended period
Result Costs in favour of respondent ($3,000)
Main Category Costs
Cases Cited Chen v Banclogix Ltd unreported, R Arthur, 19 Mar 2010, AA 128/10;Chen v KVB Kunlun New Zealand Ltd unreported, R Arthur, 7 Apr 2010, AA 159/10
Number of Pages 3